French Guiana – Supply 3 MVA generators for an oil-fired power plant

3 MVA generators for oil-fired power plant

Supplying and putting into service 3 MVA generators for an oil-fired power plant, with connection to the EDF network. Maintenance of existing engines.


This integrated contract, implemented for EDF between 2003 and 2004, includes engineering, equipment supply, construction and installation (EPCI) of 3 generators.

For this project, in the upstream phase ETE provided the engineering, technical and other specifications, supplier selection and procurement (purchasing, logistics and delivery to the worksite).

In a later phase, ETE managed all work onsite at Crique Margot, up until connection to the Guyanese electrical network. This work included: selection of service providers, work on the customer’s site, installation, tests, technical assistance and putting into service three 3 MVA generators for the EDF Crique Margot plant (Saint-Laurent du Maroni).

ETE technical teams were also in charge of the maintenance contract for three 1000 kVA engines.